New rates starting October 1, 2025
The Board of Supervisors of Toho Water Authority (Toho), approved t...
Check out Toho's Procurement Portal for all the projects we have advertised. Once registering on the portal, you can make your submissions.
Below is a list of our forecasted engineering projects
| Project Name / Description | Project Type: | Anticipated Advertise Date | Approximate Budget | Grant (Y/N) | Estimated Date to Start Construction | Estimated Project Duration |
| Mann St. Toho Utilities Relocation CIP-0997: City of Kissimmee has a project to perform road widening and improvements of Mann St, in Kissimmee. This project will impact some existing TWA utilities, which will need to be relocated before the roadway project. | IFB (Contractor) | November 2025 | $400K | N | January 2026 | 4 months |
| CL1-P-01 Old Pleasant Hill Rd/Dover Plum Ave. S. Poinciana Blvd. to Country Club Road CIP-1028: This project includes the addition of approximately 6,500 LF of 20" water main. The proposed connection points for the new main are: 1) the 24" water main located approximately 500' west of the intersection of Pleasant Hill Rd and South Dover Plum Ave. and 2) the 12" water main located at the intersection of Cypress Parkway and Marigold Ave. Toho is applying for WIFIA funds for this project. Advertisement is anticipated for Spring 2025. | IFB (Contractor) | November 2025 | $5.5M | N | January 2026 | 18 months |
| OUC Interconnect CIP-0664: Toho and OUC are considering potential potable water interconnections between the two utilities. Toho and OUC agreed to initiate hydraulic evaluations to determine how best to implement the interconnects and how much water could be delivered through the interconnects from OUC to Toho and from Toho to OUC. In parallel, Toho and OUC are working on the details of a potential agreement. Interconnect 1: extends approximately 380 feet south from OUC’s 16-inch water main on Golden Sunburst Avenue to the existing Toho 24” water main on Boggy Creek Road. Interconnect 2: Toho (Simpson Road) and OUC (Boggy Creek Road) systems are approximately 500 feet between the 16” Toho and 12” OUC water mains. | IFB (Contractor) | November 2025 | $3.8M | N | January 2026 | 6 months |
| St. Cloud Downtown WM Replacement CIP-0627: The potable water infrastructure in St. Cloud’s downtown area includes one-inch diameter galvanized steel pipe (GSP) and four and six-inch cast iron pipe (CIP), materials that are no longer used by Toho in distribution system construction and are also undersized. These mains have a greater probability of failure and can contribute to pressure issues. To address these concerns, this project will replace and upsize infrastructure at four locations in the downtown St. Cloud area. | IFB(Contractor) | November 2025 | $2.4M | Y | December 2025 | 6 months |
| St. Cloud LS Diversions CIP 1008: St. Cloud’s LS 40 has reached capacity. In response to this problem, Toho has worked with a developer to construct a 16”/20”/24” Kissimmee Park FM spanning approximately 19,000 LF and divert existing Toho East LS connected to LS40 to the Kissimmee Park FM. Plans for this force main have been completed and awaiting bid. The plans include the stub outs and diversions. | IFB (Contractor) | November 2025 | $1.88M | N | January 2026 | 12 months |
| Richard McLaughlin (NB) WRF Valve Replacement CIP-0980: Replace one 48” and two 36” isolation valves, one 30” and one 36” flow meter isolation valve, and one 36” flow meter bypass valve. Project also includes installation of a 20” bypass line, magnetic flow meter, and the replacement of the radio tower, and plant security system upgrade. | IFB (Contractor) | November 2025 | $3M to $4.0M | N | January 2026 | |
| South Side WRF Dewatering Project: Construction of new dewatering facility including centrifuge, building, cent rate lift station, biosolid pumping facilities, and related electrical improvements | RFQu (CMAR) | November 2025 | $7-8 million | N | May 2026 | 22 months |
| Southwest Water Treatment Plant Improvement | RFQu (Engineer) | November 2025 | over $ 10 millions | October 2026 | 36 months | |
| South Side WRD Expansion to 9.0 MGD: Design of an expansion of the facility from 7.6 MGD to 9.0 MGD | RFQu (Engineer) | December 2025 | $35-40 million | N | TBD | TBD |
| Lift Station 111 Screening Improvements: Project will provide improvements in pumping capacity, new wet well storage, automatic bypass pumping, and electrical improvements. | IFB (Contractor) | December 2025 | $4 million | N | February 2026 | 12 months |
| Toho Small Projects CIP-1115: this is a batch of small projects around the Toho service area. They include a 1200 LF WM extension along Carol Terrace, a 500 LF WM extension on Patricia Circle, three interconnections at Sherwood Forrest, Celebration, and KOA/Monterrey, service line replacements at Grand Palms, and installation of a driveway at the Reunion Reuse Station. | IFB(Contractor) | December 2025 | $3M | N | TBD | 8 months |
| South Poinciana Blvd. Booster Station (CL2-B-01): A booster station as part of Cypress lake Water Wheeling Infrastructure, to connect transmission mains between Poinciana Blvd. and OBT; Design 18.6 MGD booster station; site selection/land acquisition required. | RFQu (Engineer) | January 2026 | $10 million | August 2027 | 18 months | |
| Hoagland Blvd. 20" Water Main Extension CIP-0961: This project is identified in the Master Hydraulic Model updates. This project is anticipated to increase water supply service by approximately 1.29 MGD to the Poinciana service area. The 24" water main is required to transfer potable water from the Toho area to the Poinciana area to meet distribution system demands. This project includes a 24" water transmission main to run from the future Plant just north of Pleasant Hill Elementary School and south of Clay St. The 24" water main will generally be installed west of the start location along the access road north of the elementary school, south along Jack Calhoun Dr. and South Hoagland Blvd, and through Good Samaritan Village. | IFB (Contractor) or CMAR | January 2026 | $9M | N | April 2026 | 18 months |
| Northwest WTP Storage Expansion CIP-0999: Construction of a new 1.0 MG ground storage tank and associated piping, a new above grade metering station and required stormwater improvements. | IFB (Contractor) | May 2026 | $6.5 million | N | July 2026 | 14 months |
| 16" RM Old Hickory Tree Rd/10th Street/Narcoossee Rd CIP-0990: Supplement growth in the northeast service area by extending a sixteen-inch reclaimed main along Old Hickory Tree Rd to E 10th Street, east to Narcoossee Rd for a total length of approx. 12,000 feet. | IFB (Contractor) | June 2026 | $6 million | Y | August 2026 | 1 year |
| Friar's Cove Water Main CIP-0979: 19,900 LF of 24" water main along east side of Lake Tohopekaliga. Includes two turnpike crossings and connection to existing watermains. | IFB (Contractor) | October 2026 | $7.3 million | N | April 2027 | 18 months |
| Sunbridge WRF Expansion to 3.5 MGD: CMAR Construction for WRF expansion. The improvements include new pretreatment units, treatment process expansion, a new in-plant pump station, effluent transfer pumps, reclaimed water high speed service pumps, new chlorine contact chamber and biosolids and dewatering system improvements. | RFQu (CMAR) | TBD | $35 -40 million | N | January 2027 | 18 months |