Projects in the pipeline

Below is a list of our advertised and forecasted engineering projects. 

Project Name/Description Type Advertising Date

Grant (Y/N)

Harmony WRF Expansion Consultant Selection: Harmony WRF has a permitted capacity of 0.499 MGD AADF. The facility is currently undergoing construction to expand the plant to 0.75 MGD AADF. This project will increase the permitted capacity of the Harmony WRF from 0.75 MGD to approximately 1.3 MGD AADF.  RFQu Advertised - RFQu-24-048 N
Harmony WTP Well Pump Procurement: To provide eight (8) Ion Exchange vessels and associated appurtenances including, but not limited to, valves and actuators, magnetic flow meters, a blower, brine saturator system, dilution panel, and the resin, for a one-time purchase. IFB Advertised - IFB-24-070 N
Metallic Force Main Excavation and Inspection: Excavating to expose force mains at 14 locations and, once wall thickness testing is completed, then backfill, compaction and restoration be completed. IFB Advertised - IFB-24-071 N
Shingle Creek Pipe Bridge Replacement: Furnishing all labor, equipment and materials necessary to for the installation of four (4) new insertion valves, two (2) new pipe supports and the demolition of two (2) existing pipe supports. IFB Advertised - IFB-24-085 N
Lincoln Street Sewer Project: Install approximately 530 LF of 8-inch sanitary sewer main by open cut along Lincoln Street and connecting it to the existing sanitary sewer main along MLK Blvd. The project includes eight laterals, two manholes, one dog house manhole, six water services, four single water services, and site restoration. IFB Advertised - IFB-24-083 N
WTP #4 CMAR Services (Re-Bid): WTP #4 has a permitted treatment capacity of 9 MGD.  The plant is bring upgrade to improve water quality.  The upgrade project includes the replacement of the MIEX treatment system with a fixed bed ion exchange treatment system with associated sand filters for pretreatment, regeneration system, well pump improvements, and related electrical, I&C and yard piping work. RFP or IFB March N
LS 30 Renee IV-N. John Young Pkwy GS Rehab -WIFIA: Replace gravity sewer mains, laterals, and manholes, and rehabilitate, gravity sewer mains and laterals by Cured-In-Place-Pipe (CIPP) lining, and rehabilitate manholes by sealing and coating, within Lift Station 30 Basin Area. IFB March N
CL1-I-03 Champions Gate Interconnect: Located in Davenport, Osceola County, Florida, this project is a DI FM replacement resulting from an emergency break at Champions Gate Blvd falls under the category of priority CIP. The project scope includes the installation of directional drilling of a 16-inch force main project within the improved right-of-way of Champions Gate Boulevard west of I-4.  IFB March N
Pine Lake Estates: The project consist of replacing approximately 8,250 linear feet of existing 10-inch and 6-inch potable water mains with a minimum 8-inch diameter pipe, fire hydrants and related appurtenances within the Pine Lakes Estates neighborhood. IFB  March N
Pleasant Hill 16” Water Main: Between Granada Blvd. and Eagle lake Blvd. is a 2,100 ft water main gap. The mains terminating at Granada and Eagle Lake are 16 and 12 inch. The two mains are connected through adjacent residential streets via 8 and 10 inch mains. This restriction limits the movement of water into south Poinciana. The restriction will be eliminated by extending 2,100 ft of water main.The water main extension will support moving water to serve existing customers and future growth. IFB March N
Edgewater Reuse Storage and Repump Station: Toho is experiencing growth throughout its reuse service area primarily due to new developments. Toho master planning identified a new Edgewater Reuse Storage and Repump Station (Edgewater Reuse) to help meet new developments’ reuse demands. The proposed pumping capacity of the facility is 6,000 gallons per minute and the proposed storage capacity is 2.5 million gallons. RFQu March N
Sunbridge WRF Expansion to 3.5 MGD: The Sunbridge WRF Expansion to 3.5 MGD Project will be designed and constructed to expand the existing capacity of 1 million gallon per day (MGD) Average Daily Flow (ADF) to the capacity of 3.5 MGD ADF. The improvements will include overall facility components and infrastructure upgrades. RFQu March N
Lakeshore Interconnection: Install approximately 520 LF of 14” HDPE HDD, 71 LF of 12” PVC by open cut, and 45 LF of 8” PVC by open cut to interconnect Toho East (St. Cloud). IFB March N
St. Cloud Interconnection Phase II: Install approximately 2620 LF of 12” PVC WM and associated valves and hydrants to interconnect Toho East (St. Cloud). Richard Mclaughlin WRF Valve Replacement: replace one 48” and two 36” isolation valves, one 30” and one 36” flow meter isolation valve, and one 36” flow meter bypass valve. Project also includes installation of a 20” bypass line, magnetic flow meter, and the replacement of the radio tower, and plant security system upgrade. IFB March N
Richard McLaughlin WRF Valve Replacement: Replace one 48” and two 36” isolation valves, one 30” and one 36” flow meter isolation valve, and one 36” flow meter bypass valve. Project also includes installation of a 20” bypass line, magnetic flow meter, and the replacement of the radio tower, and plant security system upgrade. IFB March N
Parkway WRF Reject Pond Liner Replacement: Parkway WRF's reject storage pond liner was installed in 1990. Liners have an expected lifespan of 20 years. The liner at Parkway has failed and been repaired multiple times. Additionally, it is an FDEP requirement to have a lined reject storage pond. If the liner fails again and cannot be repaired the plant would be out of compliance. IFB March N
Northeast Booster PS Upgrade: Northeast Booster Pump Station (NESS) will be upgraded with increased pumping capacity to better maintain pressures in the City's water distribution system. Four (4) pumps will be replaced. Ductile iron piping will be replaced with larger diameter piping. The generator will be replaced with a larger one of sufficient size to provide backup power to the three (3) firm pumps. Some tank recirculation piping will be replaced with larger diameter piping. A temporary bypass pumping system will be installed during the time that the existing pump station is out of service. RFQu March N
Continuing CMAR: Selection of CMAR firm to provide continuing CMAR services treatment facility projects that are within the CCNA. RFQu March N
CMAR Pre-Qualification for Major Projects: Pre-Qualify CMAR to provide CMAR services for treatment facility that exceed CCNA limits. RFQu March  
16-inch Champions Gate Force Main Replacement: Furnishing all labor, equipment, and materials necessary to: construct 20-inch DR-11 HDPE force main via horizontal directional drilling, construct 16-inch DR-18 PVC force main via open cut, construct 18-inch SDR-26 PVC gravity sewer, construct (1) 5-FT diameter manhole (20-FT deep), connect new force main to an existing lift station wet well, rehabilitating the wet well by sealing and coating, place out of service (grout fill) existing 16-inch DIP force main, associated fittings, valves, other appurtenances and full restoration within Champions Gate Blvd project area. IFB March N
Cypress Lake Concentrate Injection Well (IW-1): Second injection well at the Cypress Lake project to dispose of brine concentrate. IFB Late March Y
Cypress Lake Raw Water Main to Connect PW 1-4 to WTP Site: Will connect four brackish water production wells to the Cypress Lake reverse osmosis water treatment plant site. IFB Late March Y
CMAR GCs & Fee bid for Sunbridge WTP Upgrade & Expansion Project: Expansion of the existing 1.0 MGD water treatment plant to 4.8 MGD. Includes addition of complete nanofiltration and degassifier processes and conversion to free chlorine disinfection. IFB Late March N
Sunbridge Water Treatment Plant Expansion: Expansion of the existing 1.0 MGD water treatment plant to 4.8 MGD.  Includes addition of complete nanofiltration and degassifier processes and conversion to free chlorine disinfection. RFQu Late March N
Nolte Road Booster Pump Station: The Nolte Road Booster Pump Station is an infrastructure improvement project intended to address ongoing pressure issues in City’s northeast potable water service area and help to accommodate demands associated with the anticipated Center Lake DRI. The Project is located in the City of St. Cloud, Florida. IFB Late March N
Florida Plaza - 192 Force Main: The force main along US-192 in the vicinity of Florida Plaza/Seralago Hotel and Suites failed at two locations in less than a two months period.  Temporary point repairs were completed to restore service. A temporary bypass force main was installed and in operation on 12/20/2023. A permanent replacement of the remaining 16-inch DIP force main will be replaced with 20-inch HDPE directional bore. The scope was expanded to add additional force main replacement.  The project is expected to bid in March 2024 and be substantially complete Sept. – Nov. 2024 RFP Late March  
Lift Station 111 Screening Improvements: Project will add screening structure and will modify side piping and electrical modifications.  IFB April N
Reedy Creek Interconnection: Modifications to the existing Reedy Creek interconnect for RCES to provide 2.5 MGD to Toho. Modifications include a new control valve, pressure gauge w/ transmitter, gave valve w/ motorized remove actuator, mag flow meter, and a control panel. IFB April N

Need help?

If you have any inquiries, please send an email to procurement@tohowater.com