What could be affecting my water bill
Toho Water Authority has seen an increase in customer questions abo...
Check out Toho's Procurement Portal for all the projects we have advertised. Once registering on the portal, you can make your submissions.
Below is a list of our forecasted engineering projects.
Project Name/Description | Type | Anticipated Advertising Date | Approximate Budget | Grant (Y/N) | Estimated Construction Start Date | Estimated Project Duration |
---|---|---|---|---|---|---|
Financial Institution Procurement for Letter of Credit for WCCF | RFP (Financial) | January 2025 | N/A | N | N/A | N/A |
Mann St. Toho Utilities Relocation: City of Kissimmee has a project to perform road widening and improvements of Mann St, in Kissimmee. This project will impact some existing Toho utilities, which will need to be relocated before the roadway project. | IFB (Contractor) | January 2025 | N | |||
Nolte Road Booster Pump Station: The Nolte Road Booster Pump Station is an infrastructure improvement project intended to address ongoing pressure issues in City’s northeast potable water service area and help to accommodate demands associated with the anticipated Center Lake DRI. The Project is located in the City of St. Cloud, Florida. | IFB (Contractor) | January 2025 | $2.5 to $3.0 million | N | ||
Smith St. Gravity Sewer Rehab: This project will furnish and install 12,000 feet of CCIP Liner for 8-inch gravity sewer and manholes. | IFB (Contractor) | February 2025 | $5.0 million | N | April 2025 | 4 months |
Shingle Creek Reserve and Bermuda Estates Gravity Sewer Rehab: This project will furnish and install 5200 feet of CCIP Liner for 8-inch gravity sewer. | IFB (Contractor) | February 2025 | $3.1 million | N | April 2025 | 3 months |
Cypress Lake Raw Water Main to Connect PW 1-4 to WTP Site: Will connect four brackish water production wells to the Cypress Lake reverse osmosis water treatment plant site. | IFB (Contractor) | February 2025 | $7M | Y | May 2025 | |
Continuing Design-Build (Multiple Projects): Toho will seek to select more than one Design-Build Firm (“DB Firm”) to undertake linear utility projects and/or treatment plant projects. This will be advertised as one solicitation or two solicitations, TBD. Toho may assign project(s) to a DB Firm via Task Authorization(s). The selected DB Firms will be responsible for completing assigned projects, which may include new construction, emergency repair projects, renewal, replacement, pump station equipment installation and other miscellaneous utility work projects. The estimated construction costs for each individual project will be less than the limit established by section 287.055(1)(g), Florida Statutes (currently, $7.5 million). | RFQu (Design-Build) | February 2025 | ||||
Harmony WRF 2.0 MGD Expansion | RFQu (CMAR) | TBD | $20M | N | Mid-2026 | 24 months |
Lake Marion WRF AST Improvements | RFQu (CMAR) | TBD | $15.5 million | N | Early 2026 | 20 months |
South Poinciana Blvd from Crescent Lakes Way to OBT: Cypress Lake Transmission Main (Segment CL2-P-04B) approximately 12,500 LF of parallel 30" pipe along South Poinciana Blvd from Crescent Lakes Way to South Orange Blossom Trail. The project includes route analysis, preliminary design, surveying and SUE services, geotechnical investigations, roadway project coordination, permitting, and bidding assistance, final design, and construction administration services. This project is located along a major arterial road which may include a high maintenance of traffic (MOT) plan. | RFQu (Engineer) | March 2025 | $12 million | N | February 2027 | 24 months |
Hoagland Blvd. 20" Water Main Extension: This project is identified in the Master Hydraulic Model updates. This project is anticipated to increase water supply service by approximately 1.29 MGD to the Poinciana service area. The 24" water main is required to transfer potable water from the Toho area to the Poinciana area to meet distribution system demands. This project includes a 24" water transmission main to run from the future Plant just north of Pleasant Hill Elementary School and south of Clay St. The 24" water main will generally be installed west of the start location along the access road north of the elementary school, south along Jack Calhoun Dr. and South Hoagland Blvd, and through Good Samaritan Village. | RFQu | March 2025 | $9M | N | July 2025 | 18 months |
Emergency Generators under Resilient Grant Application: The project consists of replacing generators at North Bermuda Main Plant Generator, North Bermuda Well #6 Generator, Camelot West Well #2 Generator, Southwest Well #1 Generator, Camelot WRF Generator, Imperial Pump Station Generator, Camelot West WTP Main Plant Generator, Southside WRF Generator near Biosolids, Parkway WTP Well #3 Generator, (4) 570 kW Portable Generators, Huron WTP Main Plant Generator, St. Cloud WTP #1 Main Plant Generator, St. Cloud WTP #2 Main Plant Generator, and St. Cloud WTP #4 Well #7 Generator. | IFB (Contractor) | March 2025 | $11M | Y | May 2025 | 24 months |
St. Cloud Downtown WM Replacement: The potable water infrastructure in St. Cloud’s downtown area includes one-inch diameter galvanized steel pipe (GSP) and four and six-inch cast iron pipe (CIP), materials that are no longer used by Toho in distribution system construction and are also undersized. These mains have a greater probability of failure and can contribute to pressure issues. To address these concerns, this project will replace and upsize infrastructure at four locations in the downtown St. Cloud area. | IFB(Contractor) | March 2025 | $2.4M | Y | May 2025 | 6 months |
Camelot WRF Blower Replacement: Replace four (4) existing HIS turbo blowers with magnetic bearing turbo blowers, repair air leak in blower piping adjacent to blower building, and replace air piping between blower building and process basin. Replace four (4) existing HIS turbo blowers with magnetic bearing turbo blowers, repair air leak in blower piping adjacent to blower building, and replace air piping between blower building and process basin. | March 2025 | $1.0 - $1.5 million | N | April 2025 | 3 months | |
Northwest WTP Storage Expansion: Construction of a new 1.0 MG ground storage tank and associated piping, a new above grade metering station and required stormwater improvements. | IFB (Contractor) | March 2025 | $6.5 million | N | May 2025 | 14 months |
South Side WRF Dewatering: Construction of new dewatering facility and in-plant lift station. | RFQu (CMAR) | March 2025 | $4.0 million | N | December 2025 | 18 months |
OUC Interconnect: Toho and OUC are considering potential potable water interconnections between the two utilities. Toho and OUC agreed to initiate hydraulic evaluations to determine how best to implement the interconnects and how much water could be delivered through the interconnects from OUC to Toho and from Toho to OUC. In parallel, Toho and OUC are working on the details of a potential agreement. Interconnect 1: extends approximately 380 feet south from OUC’s 16-inch water main on Golden Sunburst Avenue to the existing Toho 24” water main on Boggy Creek Road. Interconnect 2: Toho (Simpson Road) and OUC (Boggy Creek Road) systems are approximately 500 feet between the 16” Toho and 12” OUC water mains. | IFB(Contractor) | April 2025 | $3.8M | N | July 2025 | 6 months |
Sand Hill WRF Advanced Wastewater Treatment and Odor Control: AWT: Improvements to the existing process to meet AWT goals of 3 mg/L total nitrogen and 1 mg/L total phosphorous. Includes chemical feed systems (carbon and alum), basin wall reconfiguration, and process piping extension. Odor Control: Improvements to the existing headworks odor control system to include adding parallel biofilters and a carbon polishing system and associated piping downstream of the existing (BioAir) biotrickling filter. Includes refurbished two existing (Bioteg) carbon units for use as biofilter. Odor control to be an early deliverable package. | RFQu (CMAR) | April 2025 | $6.2 million + $650,000 | N | July 2025 (Odor) October 2025 (AWT) | 19 months |
Parkway WRF Expansion to 2.0 MGD: CMAR Construction for interim expansion from 1.5 MGD to 2.0 MGD. The improvements include new pretreatment units for screening, two new clarifiers, a new pump station to return sludge, re-lining of reject pond, reconstructing the chlorine contact chamber and renovation of operations building, pavement and ADA ramp | RFQu (CMAR) | May 2025 | $20-25 million | N | September 2025 | 14 months |
Toho Reservoir Alternative Water Source Reuse Distribution Main (aka Kindred Reuse Main): 21,000 LF of 20" reuse main from NeoCity to Kindred/Tohoqua. Includes aerial canal crossing and multiple directional bores. | IFB (Contractor) | May 2025 | $9.6 million | Y | August 2025 | 12 months |
Toho Small Projects: This is a batch of small projects around the Toho service area. They include a 1200 LF WM extension along Carol Terrace, a 500 LF WM extension on Patricia Circle, three interconnections at Sherwood Forrest, Celebration, and KOA/Monterrey, service line replacements at Grand Palms, and installation of a driveway at the Reunion Reuse Station. | IFB(Contractor) | June 2025 | $3M | N | September 2025 | 8 months |
Friar's Cove Water Main: 19,900 LF of 24" water main along east side of Lake Tohopekaliga. Includes two turnpike crossings and connection to existing watermains. | IFB (Contractor) | June 2025 | $7.3 million | N | September 2025 | 18 months |
Sunbridge WRF Expansion to 3.5 MGD: CMAR Construction for WRF expansion. The improvements include new pretreatment units, treatment process expansion, a new in-plant pump station, effluent transfer pumps, reclaimed water high speed service pumps, new chlorine contact chamber and biosolids and dewatering system improvements. | RFQu (CMAR) | July 2025 | $35 million | N | June 2026 | 18 months |
South Side WRF Headworks Improvements: Construction of new headworks screen and compactor, concrete repair, manhole replacement, in-plant lift station improvements. | RFQu (CMAR) | July 2025 | $1.9 million | N | October 2025 | 11 months |
St. Cloud LS Diversions: St. Cloud’s LS 40 has reached capacity. In response to this problem, Toho has worked with a developer to construct a 16”/20”/24” Kissimmee Park FM spanning approximately 19,000 LF and divert existing Toho East LS connected to LS40 to the Kissimmee Park FM. Plans for this force main have been completed and awaiting bid. The plans include the stub outs and diversions. | IFB(Contractor) | August 2025 | $1.88M | N | November 2025 | 12 months |
South Side WRF DO Control: Improvements to the process air system. May include diffuser replacement, blower replacement, air piping improvements, and control logic revisions. | RFQu (CMAR) | October 2025 | $4.0 million | N | December 2025 | 16 months |
Edgewater (West) Storage and Repump Facility: To increase reuse water storage and delivery capacities as well as reliability of Toho's reuse water infrastructure, construct two 2.5 MG ground storage tanks, 6,000 gpm pump station, and connect to existing 16" reclaimed water main along Cross Prairie Parkway. | IFB (Contractor) | December 2025 | $6 million | Y | March 2026 | 1 year |
16" RM Old Hickory Tree Rd/10th Street/Narcoossee Rd: Supplement growth in the northeast service area by extending a sixteen-inch reclaimed main along Old Hickory Tree Rd to E 10th Street, east to Narcoossee Rd for a total length of approx. 12,000 feet. | IFB (Contractor) | December 2025 | $6 million | Y | March 2026 | 1 year |
Richard McLaughlin (NB) WRF Valve Replacement: Replace one 48” and two 36” isolation valves, one 30” and one 36” flow meter isolation valve, and one 36” flow meter bypass valve. Project also includes installation of a 20” bypass line, magnetic flow meter, and the replacement of the radio tower, and plant security system upgrade. | IFB (Contractor) | On-Hold | $3.0 - $4.0 million | N |